Kremlin copies and implements the RMA

Corrupt workflow processes for building a 26 million Rouble Moscow warehouse.

Smacks of our RMA. I wouldn't wish that on any country!

HT The Devil's Kitchen.





No:ProcedureTime to complete:Cost to complete:
1Apply for an act of permission for use to the Department of City Planning Documentation Development at the Architecture and City Planning Committee of Moscow (MoskomArchitektura).1 dayno charge
2Request and obtain situation plan of district and conclusion for a District Land Commission from the Architecture Planning Department (APD)15 daysRUB 43,680
3Request and obtain a conclusion from Territorial Union of Land Use Regulation15 daysRUB 4,330
4Request and obtain a decision by the District Land Commission on land plot provision and city planning regulation30 daysno charge
5Request and obtain clearance of draft disposition of Prefect with the Architecture Planning Department (APD)7 daysno charge
6Request and obtain clearance of draft disposition of Prefect with the local government7 daysno charge
7Request and obtain clearance of draft disposition with the Territorial Union of Land Use Regulation7 daysno charge
8Request and obtain the disposition on preparation of an act of permission for use by the Prefect7 daysno charge
9Request and obtain a conclusion on compliance of the proposed building with specified city planning and territory use regulations152 daysRUB 4,500
10*Request and obtain technical conditions from water and sewage services45 daysRUB 17,673
11*Request and obtain technical conditions for an electricity connection with MosEnergo30 daysRUB 5,490,520
12*Request and obtain technical conditions to connect to telephone line30 daysRUB 3,000
13*Request and obtain approval from MoskomArchitektura on engineering of the facility14 daysRUB 4,500
14Request and obtain an act of permission for use from MoskomArchitectura30 daysRUB 6,700
15Request and obtain disposition of Prefect on the inception of construction design (decision on construction)60 daysno charge
16Request and obtain approval of design conditions by the Department of Well-Being of MoskomArchitektura7 daysRUB 53,300
17*Request and obtain approval of design conditions by the Department of Preparation of Project Approvals of MoskomArchitektura14 daysRUB 12,100
18*Request and obtain approval of design conditions by local government7 daysno charge
19*Request and obtain approval of design conditions by the Prefect's Office14 daysno charge
20*Request and obtain approval of design conditions by the Emergency Situation and Civil Defense Department14 daysRUB 14,728
21*Request and obtain approval of design conditions by Moscow State Expertise14 daysRUB 7,364
22*Request and obtain an act of the Moscow Geological-Geodesic Department15 daysRUB 36,700
23*Request and obtain approval of design conditions by the Sanitary Services (Rospotrebnadzor)30 daysRUB 13,800
24*Request and obtain approval of transport routes from the Moscow City Transport Agency30 daysRUB 8,837
25*Request and obtain approval from the State Inspectorate of Road Safety (GIBBD)30 daysRUB 8,837
26*Request and obtain approval from the Department of Comprehensive Well-Being of the city30 daysRUB 4,600
27*Request and obtain approval from the Department of Nature Use under State Ecological Expertise21 daysRUB 29,455
28Request and obtain Sketch No. 2 from the Moscow Geological Institute30 daysRUB 10,100
29Request and obtain approval of Sketch No. 2 from the Moscow Architecture Committee (MoskomArchitektura)30 daysRUB 4,000
30Request and obtain the construction passport from the Moscow Geological Institute30 daysRUB 8,837
31*Request and obtain approval of volumes of "outline of construction arrangement" and "GenPlan" from MoskomArchitektura30 daysRUB 6,500
32*Request and obtain approval of volumes of "outline of construction arrangement" and "GenPlan" from the Prefecture30 daysno charge
33*Request and obtain approval of volumes of "outline of construction arrangement" and "GenPlan" from the GenPlan Institute30 daysRUB 12,200
34Request and obtain Regulation No. 2 and certificate of approval of Architectural City Planning Decision30 daysRUB 3,600
35Request and obtain project approval by Moscow State Expertise60 daysRUB 58,000
36Request and obtain permission for construction (building permit)10 daysRUB 11,460
37Receive inspection by the State Inspectorate of Architecture and Construction Supervision during foundation construction1 dayno charge
38Receive inspection by the State Inspectorate of Architecture and Construction Supervision during structure construction1 dayno charge
39Receive inspection by the State Inspectorate of Architecture and Construction Supervision during engineering works1 dayno charge
40Receive inspection by the Union of Administrative Technical Inspection (UATI) – I1 dayno charge
41Receive inspection by the Union of Administrative Technical Inspection (UATI) – II1 dayno charge
42Receive inspection by Union of Administrative Technical Inspection (UATI) – III1 dayno charge
43Receive inspection by the Union of Administrative Technical Inspection (UATI) – IV1 dayno charge
44Receive inspection by the Union of Administrative Technical Inspection (UATI) – V1 dayno charge
45Receive inspection by the Union of Administrative Technical Inspection (UATI) – VI1 dayno charge
46Receive inspection by the Union of Administrative Technical Inspection (UATI) – VII1 dayno charge
47Connect to water services30 daysno charge
48*Request and receive inspection by the Energy Supervision Board1 dayno charge
49Connect to electricity and sign an agreement with Energosbyt14 daysno charge
50*Request and connect to telephone services5 daysno charge
51Request and convene the Approval Commission30 daysno charge
52Request and receive the disposition on operation of building (occupancy permit)10 daysno charge
53Request and receive plans from the Bureau of Technical Inventory (BTI)30 daysRUB 55,000
54Register the building after completion30 daysRUB 7,500

* Takes place simultaneously with another procedure.